Modi’s ambitious Bullet Train project is derailing due to land acquisition issues in Maharashtra. Only 23% of the land is acquired

Modi’s Bullet Train project runs into headwinds in land acquisition in Maharashtra

Modi’s Bullet Train project runs into headwinds in land acquisition in Maharashtra
Modi’s Bullet Train project runs into headwinds in land acquisition in Maharashtra

NHSRCL has been able to acquire 23% of land so far in Maharashtra

Prime Minister Narendra Modi’s ambitious Bullet Train project is totally derailed due to huge delays in the acquisition of land in Maharashtra. On March 4 in a press conference, the National High-Speed Rail Corporation Limited (NHSRCL) entrusted with the construction of Ahmedabad-Mumbai Bullet Train said that 95% of land acquisition in Gujarat is over and in Maharashtra, only 23% of the land acquisition for the rail tracks happened till date. The ambitious project was inaugurated jointly by Modi and Japanese PM Shinzo Abe in September 2017.

NHSRCL said that the Gujarat leg of the Ahmedabad-Mumbai bullet train may open first if it could not acquire land in Maharashtra in the next three months. NHSRCL MD Achal Khare also said the deadline of 2023 for completing the project was not feasible, and civil works on the Gujarat side were expected to be completed by 2024. The NHSRCL has acquired 95 per cent of the land for the 352 km stretch of the project in Gujarat but has been able to acquire only 23 per cent of land for the 156 km stretch in Maharashtra.

Tenders for Sabarmati and Ahmedabad stations and 18 km stretch in that city will be released on March 25, while those for Vadodara station and 7 to 8 km stretch in that city will be released in June,” Khare said.

“Of the 352 km stretch, we have acquired 95 per cent of land thanks to the cooperation of people as well as the Gujarat government,” Khare said, adding that the remaining five per cent will be acquired by mid-June. The NHSRCL has been able to acquire 23 per cent of land so far in Maharashtra. If we are able to acquire about 70 per cent to 80 per cent land in the next three months, we can start the entire project together,” he said.

If not, the NHSRCL will have to consider opening the Gujarat leg of the bullet train in the first phase and the Maharashtra leg in the second phase, he said. “There are many issues over land acquisition in Maharashtra. We are in talks with our Japanese counterparts to open the Gujarat phase of the project first,” Khare said.

The Uddhav Thackeray-led MVA government in Maharashtra which came to power in November 2019 had said after coming to power that it will review the necessity of the project. For the Gujarat leg of the project, contracts worth Rs.32,500 crore have been awarded for the construction of a 325 km stretch and five stations, Khare said. The bullet train will have eight stations in Gujarat and four in Maharashtra.

“Tenders for Sabarmati and Ahmedabad stations and 18 km stretch in that city will be released on March 25, while those for Vadodara station and 7 to 8 km stretch in that city will be released in June,” Khare said. The original deadline of completing the project in 2023 is not feasible as a year was lost due to the COVID-19 pandemic and land acquisition issues in Maharashtra, he said. “We expect to complete the civil works on the Gujarat side in four years, by 2024,” he added.

The NHSRCL will need 24 sets of rolling stock for high-speed trains, of which 18 will be imported from Japan, while 6 will be manufactured in India. “Japan has agreed to allow the manufacture of six sets of rolling stocks in India. The manufacturer in Japan will tie-up with an Indian company and make them here under the ‘Make in India‘ initiative. Talks are underway,” Khare said.

The NHSRCL MD also informed that alignment at Vadodara station has been changed due to various constraints. The new alignment will save roughly Rs.2,000 crore, he said. The foundation of the project was laid by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe in September 2017. It is expected to cut the travel time between Ahmedabad and Mumbai from the current six hours to less than three hours.

[with PTI inputs]

We are a team of focused individuals with expertise in at least one of the following fields viz. Journalism, Technology, Economics, Politics, Sports & Business. We are factual, accurate and unbiased.
Team PGurus

4 COMMENTS

  1. Uddhav says PM Modi is his elder brother and Modi allowed Uddhav to become MLC on Governors QUOTA to continue as CM of Maha !

    Pawar and Modi are bosom friends! Both protect Ambani et al properties!

    We thought elections in Maha state too would be clubbed with current election in 5 states!
    Maha Gov was abused many times by the Maha Govt gangs!

    PM Modi intends to continue decay of financial capital of India the Mumbai and shift the capital to Gujarat later.

    One should not be surprised if PM Modi announces Bharata Ratna for Sonia.

    It is shameful that PM and HM of our country were spectators under drugs mafia ruling entire Mumbai and Maha govt and SSR case was derailed Silencing Dr.S.Swamy permanently on that!!! Modi hi to mumkin hi.

  2. Not to worry. Lockdowns by Modi and lockouts by bankrupt businesses, not to mention people lockedout of jobs will ensure that the bullet train shot itself.

    Ambani and Adani are content with their private planes for travel.

  3. Lesson not for just MH, but for the people of the entire nation. Never to vote for dynasty/family controlled political parties. Their greed for power is unlimited, wouldn’t mind harming people’s interests to retain the same.

    • But then who voted to Shavsena – like you allude?
      Shavsena came a distance 3rd – that too riding on Modi’s popularity in the last Assy Elections in Maharashtra
      The D-Gang Pavar, the Italian Mafia Congress & Sena Pickpockets made an unhoy Alliance to capture power
      BJP too is to blame partly for allowing this TRIO MAFIA GOVT to survive.
      When BJP could destablize Karnataka, MP & Rajasthan Govts, Why was this TRIO MAFIA allowed to continue?
      Why no serious Investigation has been conducted in the Prashant Singh Murder?
      Why is the Vohra Committe Report implicating Sharad Pawar not being made public by the BJP Govt?
      Why was the D-Gang Chief Pavar conferred with a Padma Award by the Modi Govt?
      What compels Modi to state Sharad Pawar is my Guru & disables Modi from acting against Pawar?

LEAVE A REPLY

Please enter your comment!
Please enter your name here